The York County, Pennsylvania Department of Emergency Services are in the final build-out stages of a new, state-of-the-art, radio communications network. The system is an M/A-Com P25ip 500mhz digital trunked radio system, and is anticipated to see end user loading in 2008.
+
{{Infobox_TRS_P25P2_US_Pub_MultiCt
 +
|Owner    = York County
 +
|County    = [[York County (PA)|York]], [[Lancaster County (PA)|Lancaster]]
 +
|State    = [[Pennsylvania (US)|Pennsylvania]]
 +
|Band      = 700 [[MHz]]
 +
| <!-- using parameter "SysType"'s default value -->
 +
|SysID    = 037
 +
|WACN      = 45DDD
 +
|NAC      = ?
 +
|Callsigns = WQVY913 WQVY690 WQVY691 WQVY692 WQVY693 WQVY694
 +
|sid      = 4518
 +
|state    = pennsylvania
 +
}}
  
The new system will allow public safety users throughout the county to communicate with one another seamlessly while they carry out their respective daily missions, as well as during periods of extreme emergency and disaster. Currently, public safety professionals in the county operate with a patchwork of obsolete and unreliable radio systems in many different bands. Implementation of the new system will bring all users together onto a sturdy, trustworthy network that will serve York County deep into the 21st Century.
+
==Transition to 700mhz and Phase 2==
 +
In 2015, the York County Board of Commissioners, in response to the Middle Class Tax Relief and Job Creation Act of 2012 and it's associated "give-back" of the UHF-T band, voted to upgrade the county's P25 system, which went online for all county users in 2009. The upgrade will involve moving to available 700mhz P25 spectrum, and a transition of Phase 2 P25 trunking. Project 25 (P25) Phase 2 means that voice calls on the system will occur in TDMA, not FDMA modulation, essentially allowing two (or more) voice calls to occur simultaneously on the same frequency. This reduces the total number of frequencies needed to maintain necessary capacity on the system.  
  
York's system will employ a series twenty-two tower sites encompassing four simulcast zones and a single-site zone to provide reliable portable radio coverage in all reaches of the county. While some tower sites are situated on existing towers or structures, a handful of new towers have been erected. Also, new hardened, climate-controlled shelter buildings have been built to house the system's electronics. The simulcast timing is controlled by redundant GPS clocks located at each simulcast site. A microwave backbone will connect system sites to one another and to the control stations at the newly constructed 911 center and the back-up facility.
+
The upgrade involves the replacement of RF equipment and antennas at every tower facility, and the replacement of all end user (subscriber) terminal radios in the field. During the project, the microwave backbone is being upgraded, a new tower site is being added (Brogue), and an existing tower structure is being replaced (Fox43) due to it's age. Additionally, the Fulton site, which is stand-alone on the 500mhz system, will be absorbed as part of the south simulcast on the 700mhz system, eliminating the need for field users to manually select the tower when their location requires.
  
 +
In the database, you will notice that 700mhz sites have been added. The 700mhz system will run concurrently with the 500mhz system as agencies are transitioned to the newer system. As agencies are loaded, their talk groups will be activated on the new system. Talk groups which are active on the new system will remain active on the old system until cutover is compete, and voice calls will be carried on both systems. If you are monitoring a call on the 700mhz system, it will be using phase 2 modulation, and you would need a phase 2-capable scanner to hear the call.
  
                                        '''''Central Zone'''''
+
At this point, talk groups are unchanged, and will transfer one-for-one to the new system. However, it is rumored that the fire/EMS talk group plan and dispatcher deployment may change as cutover nears for that user group.
  
The most robust of the simulcasts, this zone employs nine tower sites and utilizes fourteen repeater channels to provide coverage for the central mass of the county, which includes Metro York, Springettsbury, Manchester, West Manchester, Spring Garden, Spry, Dallastown and Red Lion.
 
  
'''Tower Sites:''' Emergency Service Center (Pleasant Acres Road), Judicial Center (downtown York       City), Manchester Township, Pleasureville, Queen Street (Fox 43), Red Lion (TV49), Long-Term Back-Up  Facility (West Manchester Township Complex), Wrightsville Water Tank, and East Manchester Water Tank
+
==Introduction==
 +
The York County, Pennsylvania Department of Emergency Services are in the final build-out stages of a new, state-of-the-art, radio communications network. The system is an M/A-Com P25ip 500mhz digital trunked radio system, and is anticipated to see end user loading in 2008.
  
'''Frequencies:''' 500.31250, 500.36250, 500.56250, 500.61250, 500.78750, 500.86250, 501.03750 501.11250, 501.28750, 501.36250, 501.53750, 501.63750, 501.76250, 501.88750
+
The new system will allow public safety users throughout the county to communicate with one another seamlessly while they carry out their respective daily missions, as well as during periods of extreme emergency and disaster. Currently, public safety professionals in the county operate with a patchwork of obsolete and unreliable radio systems in many different bands. Implementation of the new system will bring all users together onto a sturdy, trustworthy network that will serve York County deep into the 21st Century.
 
 
 
 
                                        '''''North Zone'''''
 
 
 
Covering the northern areas of the county, the North Zone utilizes ten repeater channels from four tower sites, and provides service for Dillsburg, Yocumtown, Lake Pinchot, and Fairview.
 
 
 
'''Tower Sites:''' Dillsburg, Ramsey Hill, Reesers Summit, and Yocumtown
 
 
 
'''Frequencies:''' 500.48750, 500.53750, 500.81250, 500.91250, 501.06250, 501.31250, 501.33750 501.56250, 501.58750, 501.81250
 
 
 
 
 
                                        '''''West Zone'''''
 
 
 
The West simulcast will provide coverage for the Hanover area, as well as Spring Grove, West Manheim, Lineboro, and Heidelburg/Porters Sidling. The zone will simulcast from two towers, and employ ten repeater channels.
 
 
 
'''Tower Sites:''' Iron Ridge (Pigeon Hills), Spring Grove
 
  
'''Frequencies:''' 500.63750, 500.68750, 500.93750, 501.08750, 501.38750, 501.46250, 501.73750, 501.78750, 501.93750, 502.03750
+
York's system will employ a series twenty-two tower sites encompassing four simulcast zones and a single-site zone to provide reliable portable radio coverage in all reaches of the county. Portable and mobile radio units are equipped with the ProRoam feature, allowing the radio to transition between the five coverage zones with no input from the user, ensuring that the radio will be registered with the tower site providing the best possible signal to that radio.
  
 +
While some tower sites are situated on existing towers or structures, a handful of new towers have been erected. Also, new hardened, climate-controlled shelter buildings have been built to house the system's electronics. The simulcast timing is controlled by redundant GPS clocks located at each simulcast site. A microwave backbone will connect system sites to one another and to the control stations at the newly constructed 911 center and the back-up facility.
  
                                        '''''South Zone'''''
 
Providing signal to the ever-growing communities of southern York County, the South Zone will take advantage of two towers constructed by the Commonwealth for the state wide radio system, along with four other tower sites. This zone will provide adequate capacity with it's ten repeater channels.
 
  
'''Tower Sites:''' Crossroads (East Hopewell Township Building), Gatchelville (York 89),Lower Chanceford, Glen Rock, Shrewsbury (York 94), and Stewartstown Water Tank
+
==Related Wiki Pages==
 +
*[[York County (PA)]]
 +
*[[York County System and Site Listings]]
 +
*[[York County Talkgroup Description]]
  
'''Frequencies:''' 500.33750, 500.46250, 500.58750, 500.73750, 500.88750, 500.98750, 501.18750, 501.26250, 501.43750, 501.48750
+
==External Links==
 +
* [http://www.ycdesonline.net/ York County online]
  
  
                                        '''''Fulton Zone'''''
 
A single tower site, this system employs three repeater channels to provide coverage of the often troublesome Susquehanna River proper in extreme southeast York County. Located on the Lancaster County side of the river, it provides a clear shot upstream.
 
  
'''Frequencies:''' 502.01250, 502.36250, 502.53750
 
  
  
                                        '''''Paging'''''
 
York County's legacy paging includes one low band frequency and two UHF channels to disseminate calls to public safety workers. Upon completion of the new system, a single channel UHF POCSAG alphanumeric paging system will be deployed, eventually replacing the legacy paging entirely. Operating on a frequency of 453.600, the new paging system will simulcast from 18 of the county's 22 tower sites, providing reliable service to all first responders county-wide.
 
  
 +
Return to Wiki page: [[Trunked Radio Systems (PA)]]
  
                                        '''''Conventional'''''
+
[[Category:Pennsylvania Trunked Radio Systems]]
It is anticipated that York County will maintain very few conventional channels once cut-over to the new digital trunked system is complete. FMARS (Fire Mutual Aid Radio System, 154.280mhz) and NLEEF (National Law Enforcement Emergency Frequency, more often referred to simply as "National" 155.475mhz) base stations will be maintained for inter-county communications. It is unknown as to whether York County intends to deploy 8-TAC or U-TAC base stations for additional interoperability.
 

Revision as of 14:30, 2 August 2018

Multi-County
Public Trunked Radio System


NameYork County
OwnerYork County
Owner TypePublic
CountiesYork, Lancaster
StatePennsylvania
CountryUnited States

System Details
Band700 MHz
TypeProject 25 Phase II
ID037
WACN45DDD
NAC?

FCC Callsign(s)
WQVY913 WQVY690 WQVY691 WQVY692 WQVY693 WQVY694

System-specific links
DatabaseFCC Site Map
ForumRR Site Map

Other Resources
Trunktracking
FAQ
Trunktracking
Glossary

Wiki FAQMediaWiki
QuickRefPDF Card

Wiki HomeCollaboration Gateway → United States → PennsylvaniaYork, Lancaster Counties → York County TRS

Welcome to the York County collaboration article, a Multi-County Public Trunked Radio System located in York, Lancaster Counties, Pennsylvania, United States.
This is where you, the user, may index any articles you develop for scanning related topics for this Trunked Radio System.


  • Some talkgroups on this system may be using P25 Phase II TDMA modulation, which can only be monitored using a P25 Phase II capable scanner or receiver.
  • Click HERE for a list of scanners capable of monitoring those talkgroups.

Transition to 700mhz and Phase 2

In 2015, the York County Board of Commissioners, in response to the Middle Class Tax Relief and Job Creation Act of 2012 and it's associated "give-back" of the UHF-T band, voted to upgrade the county's P25 system, which went online for all county users in 2009. The upgrade will involve moving to available 700mhz P25 spectrum, and a transition of Phase 2 P25 trunking. Project 25 (P25) Phase 2 means that voice calls on the system will occur in TDMA, not FDMA modulation, essentially allowing two (or more) voice calls to occur simultaneously on the same frequency. This reduces the total number of frequencies needed to maintain necessary capacity on the system.

The upgrade involves the replacement of RF equipment and antennas at every tower facility, and the replacement of all end user (subscriber) terminal radios in the field. During the project, the microwave backbone is being upgraded, a new tower site is being added (Brogue), and an existing tower structure is being replaced (Fox43) due to it's age. Additionally, the Fulton site, which is stand-alone on the 500mhz system, will be absorbed as part of the south simulcast on the 700mhz system, eliminating the need for field users to manually select the tower when their location requires.

In the database, you will notice that 700mhz sites have been added. The 700mhz system will run concurrently with the 500mhz system as agencies are transitioned to the newer system. As agencies are loaded, their talk groups will be activated on the new system. Talk groups which are active on the new system will remain active on the old system until cutover is compete, and voice calls will be carried on both systems. If you are monitoring a call on the 700mhz system, it will be using phase 2 modulation, and you would need a phase 2-capable scanner to hear the call.

At this point, talk groups are unchanged, and will transfer one-for-one to the new system. However, it is rumored that the fire/EMS talk group plan and dispatcher deployment may change as cutover nears for that user group.


Introduction

The York County, Pennsylvania Department of Emergency Services are in the final build-out stages of a new, state-of-the-art, radio communications network. The system is an M/A-Com P25ip 500mhz digital trunked radio system, and is anticipated to see end user loading in 2008.

The new system will allow public safety users throughout the county to communicate with one another seamlessly while they carry out their respective daily missions, as well as during periods of extreme emergency and disaster. Currently, public safety professionals in the county operate with a patchwork of obsolete and unreliable radio systems in many different bands. Implementation of the new system will bring all users together onto a sturdy, trustworthy network that will serve York County deep into the 21st Century.

York's system will employ a series twenty-two tower sites encompassing four simulcast zones and a single-site zone to provide reliable portable radio coverage in all reaches of the county. Portable and mobile radio units are equipped with the ProRoam feature, allowing the radio to transition between the five coverage zones with no input from the user, ensuring that the radio will be registered with the tower site providing the best possible signal to that radio.

While some tower sites are situated on existing towers or structures, a handful of new towers have been erected. Also, new hardened, climate-controlled shelter buildings have been built to house the system's electronics. The simulcast timing is controlled by redundant GPS clocks located at each simulcast site. A microwave backbone will connect system sites to one another and to the control stations at the newly constructed 911 center and the back-up facility.